IGH Institute Signs Contracts with Croatian Roads Exceeding 12 Million Kuna

Lauren Simmonds

As Novac writes on the 26th of June, 2020, following the carrying out of the necessary public procurement procedures, the IGH Institute was awarded three new contracts with Croatian roads (Hrvatske ceste) for the construction supervision and reconstruction services of three traffic routes with a total value of around 12.3 million kuna.

This is a complete supervision over the construction of a highway of more than six kilometres in length through Karlovac in the direction of Split, which will improve traffic safety and capacity, especially during times of increased summer traffic. In addition, the new road will completely bypass Turanj, a settlement that has been extremely congested so far, and will connect to the already built Korana bridge. As already mentioned, IGH together with its partner will supervise the construction, and the value of the contracted work for the company stands at 4,606,992.00 kuna.

The second contract signed with Croatian roads is also for the complete supervision over the construction of the 3.2-kilometre-long bypass of Beli Manastir, which will better solve the need for the reduction of traffic, especially transit, through the very centre of Beli Manastir. This is extremely important because it is expected that the further construction of the Corridor Vc motorway will further emphasise transit traffic. The value of these contracted works for IGH amounts to 3,379,990.00 kuna. The deadline for completion of works is 22 months from commissioning.

Finally, the third contract with Croatian roads includes the supervision over the reconstruction of the new pavement structure of the state road between the settlements of Normanci and the Municipality of Petrijevci, with a total length of slightly more than 17 kilometres. Of particular interest in the project is the planned construction of 14 kilometres of new bike/cycling paths with the reconstruction and extension of 9 kilometres of pedestrian paths. The deadline for construction is 24 months, and IGH will conduct a complete inspection, while the value of the contracted work for the company amounts to 4,300,020.00 kuna.

In addition, they recently signed a contract for the supervision and quality control of the rehabilitation of the Krk Bridge worth a little more than 1,000,000.00 kuna.

IGH currently has around a thousand active contracts for the full range of services it offers, primarily in construction, making it a leading engineering company in the construction sector. Additionally, during the last and this year, IGH hired more than 100 new colleagues, which saw it exceed the number of 500 employees, and in the coming period it plans to hire even more manpower.

For more, follow our business page.

 

Subscribe to our newsletter

the fields marked with * are required
Email: *
First name:
Last name:
Gender: Male Female
Country:
Birthday:
Please don't insert text in the box below!

Leave a Comment