The office said that 59 contracts, worth a total of HRK 180 million (€24m), were signed for this purpose with 11 contractors.
Also agreed was the removal of 150 damaged family houses, which would cost HRK 14.12 million (€1.88m) and would be carried out by 12 companies.
The office has so far repaired 2,354 family houses and 910 houses are being repaired. HRK 92.89 (€12.4m) million has been spent on non-structural reconstruction and 44 companies have been hired for this purpose. It has also received 606 decisions on structural reconstruction from the Ministry of Physical Planning, Construction and State Assets.