Renewable energy sources are increasingly being harnessed on the Croatian coast, where there is ample wind and sun. In addition to wind power plants, which are multiplying every year, the construction of solar power plants is also on the rise.

There is one plant in Istria, which became operational in 2018, and three more will produce electricity in early 2020: on the islands of Cres and Vis and near Vrlika according to Morski on November 26, 2019. With investments of HRK 80 million, Croatian Electric Company (HEP) will add four new power plants to their network with a total capacity of 11.6 megawatts (MW). In the long term, they plan to complete solar power projects with a total power of 350 MW by the end of 2030.

The Kaštelir solar power plant has a capacity of 1 MW and an expected annual production of about 1.5 million kWh, which will meet the electricity needs of about 500 households. The power plant is equipped with solar panels manufactured by the Solvis company in Varaždin. This plant has been operating since December 2018. It has a contract with HROTE (Croatian Energy Market Operator) as a preferred producer within their incentive system. Here is an aerial video of the plant.

The location permit for the Cres solar power plant was obtained in June 2018 and that plant is being developed by the County of Primorje-goranska. The location of SE Cres is about 2 kilometers north of the settlement Orlec on the island of Cres. The power plant is 6.5 MW with an expected production capacity of 8.5 million kWh per year, which will meet the electricity needs of about 2,500 households. The total value of the investment is HRK 41 million. Preparatory work on the site is underway and the power plant will begin operating in 2020. Here is a simulation of the Cres power plant.

The Vis solar power plant will be located on the hill of Grizova Glavica, near the village of Žena Glava, about 3.6 kilometers southwest of the town of Vis and about 4.8 kilometers east of Komiža. HEP purchased the project from Končar-Obnovlji izvori energie (Končar Renewable Energy). The expected annual output is 4.2 million kWh, which will meet the needs of about 1,400 households. This investment is valued at HRK 25.3 million. The power plant is under construction and is expected to be operational by February 2020.

croatian_electric_hep_solar_power_02.jpg

The Vrlika Jug solar power plant represents the completion of the first phase of planned construction in the southern part of the Kosora working zone in the town of Vrlika. The power plant will have 2.1 MW of power and an estimated annual output of about 2.9 million kWh. Construction will be completed in the first half of 2020, according to HEP.

For more information on HEP solar plant projects, check out their website here.

To keep updated on renewable energy projects in Croatia, follow our Business page here and our Lifestyle page here.

 

Subscribe to our newsletter

the fields marked with * are required
Email: *
First name:
Last name:
Gender: Male Female
Country:
Birthday:
Please don't insert text in the box below!

Leave a Comment